The number most people are looking for
A full tear-out-and-replace on a standard Rowlett two-car driveway (call it 400–650 square feet) generally lands between $3,200 and $9,800 all-in — $8–$15 per square foot. Wider spreads exist, but they come from specifics you’ll recognize below, not from mystery. Pouring on open ground rather than replacing? The new-pour numbers are on the driveway cost guide.
Where the money goes
| Line item | Share of job | Notes |
|---|---|---|
| Demolition & haul-off | 15–25% | Breaking, loading and dumping the old slab — thickness and rebar in the old pour drive this |
| Base & subgrade work | 10–20% | The reason the old driveway failed; skipping it re-buys the same failure |
| Steel & forms | 10–15% | Rebar on chairs, formed edges, doweling into existing where slabs meet |
| Concrete & placing | 35–45% | Material, pump if access needs it, finishing crew |
| Joints, cure & cleanup | 5–10% | Same-day saw cuts, cure regime, site cleanup |
What pushes a Rowlett job up or down
Up: a thick or heavily-reinforced old slab (demolition time), poor drainage that needs regrading, an approach or apron in city right-of-way (permit and inspection through the City of Rowlett — we handle it), decorative finishes, and RV-grade thickness. Down: straight rectangular layouts, good street access for trucks, and bundling — a patio, walk, or shed pad poured the same day shares the mobilization cost.
Repair, partial replacement, or the whole thing?
Honest triage: isolated settled panels on sound base can sometimes be cut out and re-poured — worthwhile when the rest of the slab is healthy. But when cracking is spread across panels and joints have shifted out of plane, the base has failed, and panel-by-panel patching is the expensive way to replace a driveway over five years. That’s the call we make with you at the measure visit, in whichever direction the slab actually points. When it points at a full tear-out, what goes back down is the driveway spec we pour to in Rowlett: compacted base, rebar on chairs, and joints sawed the same day.
Timeline
Most replacements run two to four working days: day one demolition and base, day two forms and steel (plus inspection when the approach is in scope), day three the pour. Then the cure clock: walk it in a day or two, park on it after about a week. Weather moves pour day, never the price.
Want the real number for your driveway?
Measured free, written same day, held until the work is done.